This post is a part
of Last post as Hong Kong International Airport: Brief View. In this post
Construction of Hong Kong international airport is presented with few static
details about project. The underwater tunnel, world’s Largest double Decker
suspension bridge and land reclamation for highway construction on sea bed are
given here. Terminal building of HKIA was the world’s largest terminal building
when opened in 1998. Construction of terminal building was done taking typhoons
in view. Further ahead…
As
enlisted in last post the construction of this project involved two major parts
-
- Construction of Airport site and Building.
- Connecting airport to the town.
CONSTRUCTION
OF AIRPORT
The
site construction of the airport included joining both islands and forming one
bigger then both. So this work was started with blasting the rocks on the
islands. Now the excavated earth was to be used as filling material. But before
that a surface was required which was formed by using dredgers. These dredger
ships picked up the 40 ft deep loose soil from seabed and formed a surface
which was further followed by filling of excavated material. Now 12.48km² area
was available, remaining was construction of terminal building and runway. This
airport was equipped with two runways which routes the flights over the South
China Sea. Half of the Airport construction and Improvement funds are
consumed by runway, taxiways and aprons in any airport construction project.
After
doing this all next was the Passenger terminal building. Terminal building of
HKIA was the world’s largest terminal building when opened in 1998.
Construction of terminal building had to be perfect against the most
destructive force of nature “Typhoons”. For resisting the wind pressure of
200km/hour, it became necessary to provide pile foundation. Over these piles
the mild steel trusses were resting covering the whole terminal building. The
concrete piles were used for foundation purpose using massive hammer drivers.
Each of these piles were 25000 tons in weight.
CONNECTING
AIRPORT WITH POPULATED AREA
The distance between down town and airport was to be covered by providing -
- One Underwater Tunnel as western harbour crossing.
- Two Bridges as Lantau Link.
- and 8 Mile reclamation named as North Lantau Expressway.
UNDERWATER
TUNNEL
From
the side of town first obstruction was western harbour crossing which was
eliminated by providing a underwater tunnel. Precast fabricated sections of steel
and concrete were made for this construction. Each of these sections weighs
35000 tons while manufactured. It was not easy to take these sections to the
site. Hence these sections are carried to the site by floating them to the
location (having water tight seals on both faces). While on location, powerful
hydraulic jacks connects them at joint providing a water tight connection.
DOUBLE
DECKER SUSPENSION BRIDGE
At
Lantau link it was not possible to construct a underwater structure because of
heavy shipping traffic on the surface. Hence a bridge was needed but it must be
so high that it allows the big ships to cross below it. A normal bridge on the
site was not efficient to resist the high wind flow (typhoons). For eliminating
the effect of high velocity air it was decided to increase the weight of bridge
by making it double Decker. At these bridges a railway track with two lane road
is provided below 3 lane road at top. As a suspension bridge was planned to be
constructed it needed suspension wires for supporting the bridge deck.
The load
of deck was increased so wire must be enough strong to take it. Two 3ft
diameter suspension wires were provided in this bridge each of them weighing
50000 tons. It was not possible to hang such a heavy weight wire on supporting
columns after assembling it on ground. Thus section of wire was made by
repeatedly laying small wires from one end to other on top of columns on their
place.
After this construction so linked bridge is designated as world’s longest double
Decker suspension bridge. Finally after five years of the commencement of
project the bridge was complete.
For connecting the bridge and tunnel, a highway is needed rather than existing
highway. Hence this 6 miles distance was provided with an elevated highway and
construction of this portion was carried out only at nights preventing the
public from disturbances.
LAND
RECLAMATION AT COASTAL LINE
Reclamation
of Land for 8 miles North Lantau Expressway was a challenging work but to be
completed at any cost for traffic interaction from town to airport. The route
selected for construction of expressway was at the sea shore. The rocky ground
surface available was difficult for construction and having steeper slope. So
this rocky region was extended nearby half mile on seabed with the help of
blasting the surface rocks and dredgers. So formed horizontal surface was
taking the highway as well as the railway line. This last stretch of 8 miles
allowed the connection between town and airport.
The
Dead line of the project was so near when all this had completed. There was not
enough time to establish remaining whole system of the airport as air traffic
control system, flight display, Custom Screening and Security. Hence on 6th
July 1998 the lights of old airport was switched off and whole of the system
was transferred to the new one in a night. At 7th July 1998, first
flight from Newyork landed on the new airport.
In 2010, a huge typhoon attacked on airport, but the largest enclosed structure
was nailed to the seabed with massive concrete piles and just a minimal damage
was caused. This project is a great example of extreme engineering. Lessons
learned during this construction are valuable amd its likely to be impossible
to create such a structure in such circumstances.
For your feedback and any addition to above article please feel free to share
your comments below. For further construction related articles keep in touch
and keep reading. If you liked the post then please share and comment and if
not then please suggest us with your feedback.
for your feedback and suggestions you may also like and suggest us on our facebook page
>>
https://www.facebook.com/Dezigntheworld
just like n share to be in touch
for your feedback and suggestions you may also like and suggest us on our facebook page
>>
https://www.facebook.com/Dezigntheworld
just like n share to be in touch
No comments:
Post a Comment